Piney Run Watershed Study Timeline
Piney Run Watershed Study Timeline
- January 22, 2018 – MDE Notifies County of the requirement to evaluate Piney Run and mitigate issues by August 2027
- December 2018 – County applies for NRCS grant funding to support Watershed Study
- May 2019 – NRCS awards grant to Carroll County
- July 11, 2019 – Commissioners award the contract to AECOM
- September 10, 2019 – Contract issued to AECOM to begin work
- October 11, 2019 – Carroll County Times Article regarding study
- February 25, 2020 – Public meeting at South Carroll Senior Center
- February 25, 2021 – Briefing to County Commissioners
- March 1, 2021 – Carroll County Times Article regarding study
- March 11, 2021 – Carroll County Times Article regarding study
- March 11, 2021 – Two virtual public meetings
- March 16, 2021 – Public presentation to Planning & Zoning Commission
- March 18, 2021 – Commissioners select Alternative 1 – Compliance
- September 2021 – Watershed Study contract complete
- December 2021 – Application to NRCS for design funding